Why it’s important to understand the process of plan approval and documentation before you start the construction process, both commercial and residential.
If you have clear knowledge about what documents are needed and the office you have to visit to get an approval. Usually how many days it takes to complete your documents. What legal documents should you follow to get your plan approval?

1.Property verification
(e-Khata or e-aasthi certificate) Ownership proof required by “BBMP” or MUNICIPAL BODIES. Get this in “BBMP e-aasthi portal” for Bangalore. Respective cities/district revenue office. Documents: sale deed, aadhar, tax receipts, encumbrance certificate (EC).
Usually it takes 3-10 days.
2.Site and zoning preparation for your plan approval
Ensure site size, road width, setback, FAR compliance pre “Revised master plan” (RMP).
Office: BBMP town planning (Bangalore) local district town planning office.
Documents: Survey sketch, land use certificate, clearance if plot is in zoned commercial.
3.Architectural and structural plan
Hiring licensed engineers and architects. Prepare-soil test, floor plans, elevations, for structure stability certificate.
Applicable for both residential and commercial.

4.Application submission for plan approval (BBMP/MUNICIPAL)
Inside Bangalore:
Use BBMP OBPAS (EoDB-OBPAS portal), and NAMBIKE NAKSHE for up to 50×80 ft sites.
Upload required documents, pay scrutiny and license fees, get provisional clearance. (Artificial intelligence verifies plans for compliance).
Site inspection by BBMP civil engineers within 5-7 days, final approval within 15 days, if delayed Deemed approval.
Another district:
Submit to the local municipal corporation or town planning department, follow the similar procedures.
Timeline: usually 15-30 working days, depending on the city.
5.Additional NOCs (mainly applicable for commercial construction)
Commercial projects or large residential (>20 units or > 2000sqm build-up) be needed.
- Fire NOC.
- KSPCB CFO for “pollution”
- Airport authority NOC (if its within 10km radius of airport)
- BMRCL/BSNL NOC
- BESCOM/BWSSB NOC
1-2 Months depending on how fast you collect NOCs.
6.COMMENCEMENT CERTIFICATE (CC)
Need before starting construction-issued after plan approval or sanction.
Usually issued for 2 years or expended.
7.Periodic Affidavits and inspection
BBMP ward officer inspects periodically, every 3 months during construction

8.Occupancy certificate (OC)
Rechecking after completing construction and site clearance. includes as builds- as drawing, plan, photographs. Issued within 10-17 days for compliant project; otherwise, stoppage.
| Verification | Authority | Timeline |
| e‑Khata Verification | BBMP/Municipality | 3-10 days |
| Survey & Zoning Check | BBMP TD/District TP | 3-5 days |
| Plan Preparation | Architect | 7-10 days |
| Application & Approval | BBMP/Corporation | 15-30 days (fast in Bangalore) |
| Additional NOCs (if needed) | Fire Department, KSPCB, AAI, BESCOM, BWSSB | 1-2 Months |
| Commencement Certificate | BBMP/Local Planner | 7-10 days |
| Construction Inspections | BBMP Ward Office | Every 3 months while construction |
| Occupancy Certificate | BBMP | 10-17 days |

Portals and contacts
- KSCBP, AAI, FIRE, BDA. Municipal TP website
- BBMP (e-khata portal)
- BBMP Plan approval (bpas.bbmpgov.in)
- Sakala grievance portal (to track delay)
Plan approval is a must before starting a commercial or residential construction. Have knowledge of this plan approval process and documentation, for a smooth and transparent way and save time.